Schedule

Back Home Next

This page contains a list of scheduled project events, and key milestones and deliverables.

In addition, we maintain the following prioritized lists of what we're working on this week, and what we plan to do next week:

 

This week

  1. completing batik pattern categories
  2. automating website generating process
  3. updating courses for dissemination of the art of batik painting
  4. discussion with potential incubator to gather requirements
  5. first upload (draft)

Next week

  1. developing user interface
  2. building pattern submit, opinion posting, bulletin board, pattern auction, member registration, pattern gallery, chatting room
  3. creating outline for scheduled periodical report on database connectivity
  4. network development, finding partners 
Back to Top

Example of Mandelbrot set

Events

Wednesday 10/4/00, 1:30 pm

Monthly project review.
Location: main office room.

Friday 10/6/00, 10:00 am

Pattern design method presentation at online. First upload.
Location: website.

Back to Top

Milestones and Deliverables

Q1 -- Feasibility study, business model/plan,  and working prototype of new system

Progress: 10% (on-going).
Summary report and  prototype (.ppt) available.

Q3 -- Report on user interface menus and pattern gallery

2/3 done.
Projected completion: September 29th.

Q4 -- Selection of standard pattern design software.

On track.
Projected ship date: December 11th.

Back to Top

Batikpattern.com (c) 2000. Copyright at V. Christianto. All rights reserved.
For problems or questions regarding this web contact [Webmaster].
Last updated: Juli 14, 2000.